Relocation and expansion of the library
Federal contribution
$30,986
Federal share33%
of $93.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 21, 2018
201920202021
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Bristol
- Construction start
- Feb 15, 2019(actual)
- Construction end
- Feb 17, 2021(actual)
Against the original forecast
- Construction start8 weeks earlyforecast Apr 15, 2019
- Construction end14 months lateforecast Dec 31, 2019
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52086 in the federal list. How to read these figures.