Schedule

Announced and approvedJul 21, 2018
201920202021
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Municipality of Bristol
Construction start
Feb 15, 2019(actual)
Construction end
Feb 17, 2021(actual)

Against the original forecast

  • Construction start8 weeks earlyforecast Apr 15, 2019
  • Construction end14 months lateforecast Dec 31, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52086 in the federal list. How to read these figures.