Renovation of the municipal library

Gracefield, Quebec

completeCultureSCF
Federal contribution
$11,466
Federal share33%

of $34.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 9, 2018
201920202021
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Gracefield
Construction start
Jul 9, 2019(actual)
Construction end
Mar 25, 2021(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Aug 5, 2019
  • Construction end17 months lateforecast Nov 7, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52087 in the federal list. How to read these figures.