Interior refurbishment of the municipal library
Federal contribution
$65,523
Federal share33%
of $196.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 4, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Duhamel
- Construction start
- Jan 1, 2019(actual)
- Construction end
- Feb 11, 2021(actual)
Against the original forecast
- Construction start8 months earlyforecast Sep 4, 2019
- Construction end6 weeks lateforecast Dec 31, 2020
Also in Duhamel
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52092 in the federal list. How to read these figures.