Rehabilitation of the Recreation Centre Floor

Sainte-Hélène-de-Kamouraska, Quebec

completeRecreationSCF
Federal contribution
$3,342
Federal share33%

of $10.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 21, 2018
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 1, 2018(actual)
Construction end
Nov 9, 2018(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 1, 2018
  • Construction end6 weeks lateforecast Sep 30, 2018

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52155 in the federal list. How to read these figures.