completePublic TransitPTIF
Federal contribution
$44,165
Federal share49%

of $90.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 13, 2019
2019
Built

Approved 11 months before the announcement.

Program
Public Transit Infrastructure Fund
Ultimate recipient
City of Morden
Construction start
Apr 1, 2018(actual)
Construction end
Dec 21, 2018(actual)

Against the original forecast

  • Construction end5 weeks lateforecast Nov 15, 2018