Sanitary Sewer & Septic Tank - Cobbler Tickle
Brighton, Newfoundland and Labrador
Federal contribution
$86,102
Federal share27%
of $317.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
201920202021
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Brighton
- Construction start
- Jul 10, 2020(actual)
- Construction end
- Dec 15, 2020(actual)
Against the original forecast
- Construction end13 months earlyforecast Dec 31, 2021