Lift Station Upgrades
Trepassey, Newfoundland and Labrador
Federal contribution
$49,549
Federal share21%
of $231.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 6, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Trepassey
- Construction start
- Oct 15, 2019(actual)
- Construction end
- Apr 15, 2021(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2019
- Construction end2 weeks lateforecast Mar 31, 2021
Also in Trepassey