Watermain Installation Phase 4
Stoneville, Newfoundland and Labrador
Federal contribution
$150,990
Federal share20%
of $766.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
20192020
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Local Service District of Stoneville
- Construction start
- Sep 23, 2019(actual)
- Construction end
- Sep 18, 2020(actual)
Against the original forecast
- Construction start3 months lateforecast Jul 1, 2019
- Construction end7 weeks lateforecast Jul 30, 2020
Also in Stoneville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52207 in the federal list. How to read these figures.