Chlorination/Pumphouse Building
Hughes Brook, Newfoundland and Labrador
Federal contribution
$189,460
Federal share31%
of $612.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 10, 2018
20192020
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Hughes Brook
- Construction start
- Sep 4, 2019(actual)
- Construction end
- Mar 13, 2020(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 1, 2019
- Construction end9 months earlyforecast Nov 30, 2020