Back to projects

Storm Surge Disaster Mitigation

Cow Head, Newfoundland and Labrador

completeDisaster MitigationSCF
Federal contribution
$73,443
Federal share33%

of $222.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 10, 2018
2019
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Cow Head
Construction start
Jul 29, 2019(actual)
Construction end
Sep 1, 2019(actual)

Against the original forecast

  • Construction start13 months lateforecast Jul 8, 2018
  • Construction end15 months earlyforecast Nov 30, 2020