Water Infrastructure Upgrades
Herring Neck, Newfoundland and Labrador
Federal contribution
$28,924
Federal share24%
of $122.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 10, 2018
201920202021
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Local Service District of Herring Neck
- Construction start
- Aug 1, 2020(actual)
- Construction end
- Jan 4, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 1, 2020
- Construction end3 months earlyforecast Mar 31, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52234 in the federal list. How to read these figures.