Extension of highway 19 between highways 440 in Laval and 640 in Bois-des-Filion

Bois-des-Filion, Quebec

underwayHighways and RoadsNRP
Federal contribution
$260.4M
$260,435,500
Federal share31%

of $838.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 13, 2019
today
20192021202320252027
BuiltForecast

Approved 7 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Nov 19, 2021(actual)
Construction end
Sep 30, 2027(forecast)

Against the original forecast

  • Construction start7 weeks lateforecast Oct 1, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52358 in the federal list. How to read these figures.