Expansion of the Saint-Bonaventure Library

Saint-Bonaventure, Quebec

completeCultureSCF
Federal contribution
$121,333
Federal share33%

of $364.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 11, 2018
201920202021
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Oct 10, 2018(actual)
Construction end
Aug 19, 2021(actual)

Against the original forecast

  • Construction start24 months earlyforecast Sep 30, 2020
  • Construction end5 months lateforecast Mar 30, 2021