Upgrading of the wastewater treatment system

Roberval, Quebec

completeCultureSCF
Federal contribution
$512,651
Federal share33%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 15, 2018
201920202021
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Roberval
Construction start
Jul 15, 2018(actual)
Construction end
Aug 25, 2021(actual)

Against the original forecast

  • Construction end2.7 years lateforecast Dec 15, 2018

Also in Roberval

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52514 in the federal list. How to read these figures.