Installation of wastewater treatment equipment at the sanitary block at the Sainte-Rose-du-Nord wharf
Federal contribution
$133,916
Federal share33%
of $401.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 14, 2018
2019202120232025
BuiltForecast
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Municipality of Sainte-Rose-du-Nord
- Construction start
- Jul 1, 2018(actual)
- Construction end
- Jun 20, 2026(forecast)