Northern Water System Upgrades

Creighton, Saskatchewan

completeDrinking WaterNRP
Federal contribution
$3.7M
$3,732,837
Federal share33%

of $11.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2019
202020212022202320242025
Built

Approved 4 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Sep 1, 2020(actual)
Construction end
Dec 31, 2024(actual)

Against the original forecast

  • Construction end5 months lateforecast Jul 31, 2024

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52551 in the federal list. How to read these figures.