Northern Water System Upgrades
Federal contribution
$3.7M
$3,732,837
Federal share33%
of $11.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 5, 2019
202020212022202320242025
Built
Approved 4 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Northern Municipal Trust Account
- Construction start
- Sep 1, 2020(actual)
- Construction end
- Dec 31, 2024(actual)
Against the original forecast
- Construction end5 months lateforecast Jul 31, 2024
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52551 in the federal list. How to read these figures.