Vehicle Acquisition (Phase 1)

Undefined, British Columbia

completePublic TransitPTIS
Federal contribution
$24.8M
$24,803,102
Federal share39%

of $63.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 16, 2018
2019202020212022
Built

Approved 4 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
British Columbia Transit
Construction start
Apr 1, 2019(actual)
Construction end
Jun 30, 2022(actual)

Against the original forecast

  • Construction start9 months lateforecast Jul 5, 2018
  • Construction end9 months earlyforecast Mar 31, 2023

Also in Undefined

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52556 in the federal list. How to read these figures.