Sewage Lagoon Construction

Arlington No. 79, Saskatchewan

completeWastewaterSCF
Federal contribution
$253,333
Federal share33%

of $760.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
20192020202120222023
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Aug 23, 2021(actual)
Construction end
Jun 25, 2023(actual)

Against the original forecast

  • Construction start5 months lateforecast Apr 1, 2021