Back to projects

Lagoon Expansion

Gerald, Saskatchewan

completeWastewaterSCF
Federal contribution
$148,333
Federal share33%

of $445.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Gerald
Construction start
Sep 7, 2020(actual)
Construction end
Nov 4, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast May 25, 2020
  • Construction end4 weeks earlyforecast Nov 30, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52575 in the federal list. How to read these figures.