Lagoon Expansion

Lemberg, Saskatchewan

completeWastewaterSCF
Federal contribution
$697,918
Federal share26%

of $2.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
20192020202120222023
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Lemberg
Construction start
May 21, 2020(actual)
Construction end
Dec 31, 2022(actual)

Against the original forecast

  • Construction start12 months lateforecast Jun 1, 2019
  • Construction end6 months lateforecast Jun 30, 2022