Water Treatment Upgrade
Federal contribution
$688,333
Federal share33%
of $2.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
201920202021
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Village of Coleville
- Construction start
- Sep 9, 2019(actual)
- Construction end
- Mar 21, 2021(actual)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52592 in the federal list. How to read these figures.