Treatment Plant Expansion and Upgrade
Federal contribution
$576,766
Federal share33%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2018
2019202020212022
Built
Approved 3 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Bengough
- Construction start
- Sep 30, 2019(actual)
- Construction end
- Mar 31, 2022(actual)
Against the original forecast
- Construction start7 weeks lateforecast Aug 12, 2019
- Construction end12 months lateforecast Mar 31, 2021
Also in Bengough