Emma Lake Wastewater System

Lakeland No. 521, Saskatchewan

completeWastewaterSCF
Federal contribution
$1.2M
$1,180,836
Federal share33%

of $3.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
2019202020212022
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Sep 1, 2020(actual)
Construction end
Jun 29, 2022(actual)

Against the original forecast

  • Construction start4 months lateforecast May 1, 2020
  • Construction end3 months lateforecast Mar 31, 2022

Also in Lakeland No. 521

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52599 in the federal list. How to read these figures.