Back to projects

Alameda Dam Road Upgrade

Moose Creek No. 33, Saskatchewan

completeHighways and RoadsSCF
Federal contribution
$161,725
Federal share31%

of $528.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 11, 2018
20192020
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 6, 2020(actual)
Construction end
Oct 30, 2020(actual)

Against the original forecast

  • Construction start3 months earlyforecast Oct 1, 2020
  • Construction end5 months earlyforecast Mar 21, 2021