The Buffalo Pound Water Treatment Plant Electrical Capital Upgrade
Federal contribution
$10.3M
$10,291,000
Federal share33%
of $30.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 9, 2018
201920202021202220232024
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Buffalo Pound Water Treatment Corporation
- Construction start
- Apr 10, 2019(actual)
- Construction end
- May 31, 2024(actual)
Against the original forecast
- Construction end8 months lateforecast Sep 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52614 in the federal list. How to read these figures.