Western Valley Multiplex
Federal contribution
$1.8M
$1,825,275
Federal share60%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 30, 2018
20192020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Village of Centreville
- Construction start
- Sep 1, 2018(actual)
- Construction end
- Mar 31, 2020(actual)
Against the original forecast
- Construction start6 weeks earlyforecast Oct 15, 2018
Also in Centreville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52615 in the federal list. How to read these figures.