Schedule
Announced and approvedAug 22, 2019
2019202120232025
Built
Approved 12 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Rural Community of Saint-André
- Construction start
- May 20, 2025(actual)
- Construction end
- Nov 28, 2025(actual)