Turbine and Generator Upgrades at the Snare Forks Powerhouse

Behchokö (Rae-Edzo), Northwest Territories

completeGreen EnergyGIS
Federal contribution
$9.5M
$9,493,148
Federal share75%

of $12.7M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2018
2019202020212022
Built

Approved 8 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
NT Hydro
Construction start
Dec 1, 2018(actual)
Construction end
Feb 22, 2022(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast Jan 1, 2019
  • Construction end7 months lateforecast Jul 25, 2021