Bridge Replacements on Routes 1, 10 and 100
Clarenville, Newfoundland and Labrador
Federal contribution
$8.8M
$8,800,000
Federal share50%
of $17.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 30, 2019
201920202021202220232024
Built
Approved 11 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Construction start
- Nov 1, 2018(actual)
- Construction end
- Nov 30, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Oct 1, 2018
- Construction end4 weeks lateforecast Oct 30, 2023
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52720 in the federal list. How to read these figures.