Bow Valley Mountain Creeks Flood Mitigation

Bighorn No. 8, Alberta

underwayDisaster MitigationDMAF
Federal contribution
$13.8M
$13,760,000
Federal share40%

of $34.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 13, 2019
today
20192021202320252027
BuiltForecast
Program
Disaster Mitigation and Adaptation Fund
Construction start
Aug 9, 2019(actual)
Construction end
Dec 30, 2027(forecast)

Against the original forecast

  • Construction start4 months lateforecast Apr 1, 2019

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52809 in the federal list. How to read these figures.