Wildfire Risk Reduction and Capacity Development in Northern Saskatchewan

Undefined, Saskatchewan

underwayDisaster MitigationDMAF
Federal contribution
$19.8M
$19,802,475
Federal share50%

of $39.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 23, 2019
today
20192021202320252027
BuiltForecast
Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
SaskPower
Construction start
Dec 2, 2019(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start8 weeks lateforecast Oct 8, 2019

Also in Undefined

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52815 in the federal list. How to read these figures.