Flood Control Strategy

Saskatoon, Saskatchewan

underwayDisaster MitigationDMAF
Federal contribution
$21.6M
$21,600,000
Federal share40%

of $54.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2019
today
2019202220252028
BuiltForecast

Approved 5 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
City of Saskatoon
Construction start
Jun 1, 2020(actual)
Construction end
Mar 31, 2030(forecast)

Against the original forecast

  • Construction start23 months lateforecast Jul 2, 2018