Rehabilitation of the Chemin de fer de la Gaspésie rail line between Port-Daniel-Gascons and Gaspé

Chandler, Quebec

underwayDisaster MitigationDMAF
Federal contribution
$45.8M
$45,815,200
Federal share50%

of $92.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 26, 2019
today
2020202220242026
BuiltForecast

Approved 3 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Dec 5, 2022(actual)
Construction end
Dec 31, 2026(forecast)