Infrastructure development project to protect Highway 132 against coastal hazards

Cloridorme, Quebec

underwayDisaster MitigationDMAF
Federal contribution
$13.2M
$13,200,500
Federal share43%

of $31.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 14, 2019
today
20192022202520282031
BuiltForecast

Approved 5 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Sep 10, 2018(actual)
Construction end
Oct 31, 2030(forecast)