Replacement of Provincial Highway Bridges

Corner Brook, Newfoundland and Labrador

underwayDisaster MitigationDMAF
Federal contribution
$15.2M
$15,180,000
Federal share50%

of $30.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2019
today
2019202220252028
BuiltForecast

Approved 8 weeks before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Construction start
Aug 6, 2021(actual)
Construction end
Mar 30, 2030(forecast)

Against the original forecast

  • Construction start15 months lateforecast May 1, 2020

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52867 in the federal list. How to read these figures.