Prairie North Regional Potable Water Supply Systems

Lashburn, Saskatchewan

completeDrinking WaterNRP
Federal contribution
$4.1M
$4,077,740
Federal share33%

of $12.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 26, 2019
20192020202120222023
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Ultimate recipient
SaskWater
Construction start
Dec 1, 2021(actual)
Construction end
Jan 31, 2023(actual)

Against the original forecast

  • Construction start4 months earlyforecast Apr 1, 2022
  • Construction end4 weeks lateforecast Dec 31, 2022