Grand Forks and Regional District of Kootenay Boundary Flood Mitigation

Grand Forks, British Columbia

completeDisaster MitigationDMAF
Federal contribution
$20.0M
$19,987,653
Federal share40%

of $50.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 26, 2019
2019202120232025
Built

Approved 2 months before the announcement.

Program
Disaster Mitigation and Adaptation Fund
Ultimate recipient
City of Grand Forks
Construction start
Sep 1, 2021(actual)
Construction end
May 14, 2026(actual)

Against the original forecast

  • Construction start2 years lateforecast Sep 2, 2019
  • Construction end5 months lateforecast Nov 30, 2025

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52888 in the federal list. How to read these figures.