Sanitary Sewer System Repair and Replacement

Bay de Verde, Newfoundland and Labrador

completeWastewaterSCF
Federal contribution
$78,584
Federal share33%

of $235.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
201920202021202220232024
Built

Approved 10 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Bay de Verde
Construction start
Oct 24, 2022(actual)
Construction end
Oct 26, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Aug 1, 2022
  • Construction end4 weeks lateforecast Sep 30, 2023