City of Windsor Disaster Mitigation and Infrastructure Enhancement
Federal contribution
$32.1M
$32,090,691
Federal share40%
of $80.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2019
today
20192022202520282031
BuiltForecast
Approved 4 weeks before the announcement.
- Program
- Disaster Mitigation and Adaptation Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Jun 10, 2019(actual)
- Construction end
- Sep 30, 2032(forecast)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2019
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52931 in the federal list. How to read these figures.