Kootenay Lake Ferry Service Improvements
Federal contribution
$17.2M
$17,176,667
Federal share16%
of $106.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2019
today
20192021202320252027
BuiltForecast
Approved 5 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Dec 1, 2020(actual)
- Construction end
- Mar 31, 2027(forecast)
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52946 in the federal list. How to read these figures.