Trans Labrador Highway - Route 510:Hard Surfacing of Phase III – 80 km east of Happy Valley-Goose Bay towards 160 km east of Happy Valley-Goose Bay (80 km section)

Undefined, Newfoundland and Labrador

completeHighways and RoadsNRP
Federal contribution
$11.0M
$10,979,448
Federal share50%

of $22.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 18, 2021
20202021
Built

Approved 2.2 years before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
May 1, 2019(actual)
Construction end
Sep 18, 2021(actual)

Against the original forecast

  • Construction start4 weeks earlyforecast May 31, 2019
  • Construction end3 weeks lateforecast Aug 30, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52956 in the federal list. How to read these figures.