Trans Labrador Highway - Route 510:Hard Surfacing of Phase III 80 km east of Happy Valley-Goose Bay towards 160 km east of Happy Valley-Goose Bay (80 km section)
Undefined, Newfoundland and Labrador
Federal contribution
$11.0M
$10,979,448
Federal share50%
of $22.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 18, 2021
20202021
Built
Approved 2.2 years before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Construction start
- May 1, 2019(actual)
- Construction end
- Sep 18, 2021(actual)
Against the original forecast
- Construction start4 weeks earlyforecast May 31, 2019
- Construction end3 weeks lateforecast Aug 30, 2021
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52956 in the federal list. How to read these figures.