Road Rehabilitation - Trans Canada Highway

Clarenville, Newfoundland and Labrador

completeHighways and RoadsNRP
Federal contribution
$9.6M
$9,603,000
Federal share50%

of $19.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 30, 2019
2020202120222023
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Aug 20, 2019(actual)
Construction end
Dec 20, 2022(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 30, 2019
  • Construction end11 months earlyforecast Nov 30, 2023