Rural 44 Waterlines

Eston, Saskatchewan

completeDrinking WaterNRP
Federal contribution
$6.2M
$6,213,559
Federal share33%

of $18.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2019
202020212022202320242025
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Apr 1, 2021(actual)
Construction end
Aug 7, 2025(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Mar 1, 2021
  • Construction end5 weeks lateforecast Jun 30, 2025