Sack-A-Wa Multipurpose Training Facility
Federal contribution
$436,225
Federal share30%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 12, 2019
20192020
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Sack-A-Wa Canoe Club
- Construction start
- Jul 5, 2019(actual)
- Construction end
- Aug 15, 2020(actual)
Against the original forecast
- Construction start5 months lateforecast Feb 1, 2019
- Construction end7 months lateforecast Dec 31, 2019
Also in Halifax
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52973 in the federal list. How to read these figures.