Champagne and Aishihik First Nation Administration Building Green Energy Building Retrofits

Champagne and Aishihik First Nations, Yukon

completeAdministration, Emergency and Public WorksSCF
Federal contribution
$193,057
Federal share43%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2019
201920202021
Built

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 15, 2019(actual)
Construction end
Mar 30, 2021(actual)

Against the original forecast

  • Construction end4 months earlyforecast Jul 21, 2021

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52974 in the federal list. How to read these figures.