Selkirk First Nation Early Childhood Development Centre
Federal contribution
$1.1M
$1,125,000
Federal share75%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 24, 2019
2019202120232025
Built
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Selkirk First Nation
- Construction start
- May 1, 2024(actual)
- Construction end
- Dec 22, 2025(actual)
Against the original forecast
- Construction end3 weeks lateforecast Dec 1, 2025