Yukon Government Building Energy Retrofits

Carcross, Yukon

completeOtherSCF
Federal contribution
$34.7M
$34,725,000
Federal share75%

of $46.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2019
2019202120232025
Built

Approved 8 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Government of Yukon
Construction start
Jan 10, 2019(actual)
Construction end
Mar 31, 2026(actual)