Lagoon Expansion and Upgrade

Francis, Saskatchewan

completeWastewaterSCF
Federal contribution
$173,183
Federal share29%

of $600.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 5, 2019
2020
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Francis
Construction start
Sep 8, 2020(actual)
Construction end
Dec 6, 2020(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 8, 2020
  • Construction end4 months earlyforecast Mar 31, 2021

Also in Francis