Highway 3, Jaffray Westbound Passing Lane
Federal contribution
$3.0M
$3,015,927
Federal share40%
of $7.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2019
today
2020202220242026
BuiltForecast
Approved 2 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Dec 1, 2019(actual)
- Construction end
- Oct 1, 2026(forecast)
Against the original forecast
- Construction start5 months earlyforecast May 11, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53136 in the federal list. How to read these figures.