Alaska Highway 97 and Swanson Lumber Road Intersection Improvements
Fort St. John, British Columbia
Federal contribution
$4.7M
$4,650,852
Federal share50%
of $9.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 3, 2019
20202021202220232024
Built
Approved 4 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- Sep 8, 2020(actual)
- Construction end
- Oct 31, 2023(actual)
Against the original forecast
- Construction start3 months earlyforecast Nov 30, 2020
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 53197 in the federal list. How to read these figures.